Home / Completed Projects / Improvement of drinking water supply systems in Karakalpakstan

Improvement of drinking water supply systems in Karakalpakstan

Assignment name:

«Improvement of drinking water supply systems in Republic of Karakalpakstan. Replacement of pumping equipment at water treatment plant Tuyamuyun-Nukus»

Detail Design Documentation.

Country: Republic of Uzbekistan

Location within country: Republic of Karakalpakstan

Количество привлеченных специалистов: 4
Name of Client: «ITT Flygt AB»

Date started of works:

2006

End date:

2006

Narrative description of Project:

The pumping equipment was replaced at pump stations of water treatment plant Tuyamuyun-Nukus, capacity - 170,000m3/day.

The project provides:

  • For the Pump station of I rise:

Replacement of 4 pumps Q=6,300m3/hour, H=27m, check valves D=800mm, butterfly valves D=800mm, 1,000mm and 1,200mm and also drainage pump Q=100m3/hour, H=20m.

  • For the Sludge pumping station:

Replacement of 3 pumps Q=800m3/hour, H=32m with pipeline binding.

  • For the Flushing pump station of horizontal flow sedimentation tanks:

Replacement of pumps Q=1,300m3/hour, H=65m with pipeline binding.

Description of actual services provided in the assignment:

Full package of the design-budget documents is developed. Selection of pump was carried out. Installation of pumps, pipelines and valves were carried out. Adjusting and commissioning of equipment is also carried out.